Jump to content
🌐 Shqip
From rama.exposed, the public-record investigative archive
Procurement and judicial status (as of 24 November 2026)
The European Commission's Albania 2026 Report (4 November 2026) confirmed that the state-funded Porto Romano commercial port tender was cancelled and no concrete steps had been taken to relocate cargo from Durrës. While SPAK's 16 November 2026 indictment of Belinda Balluku and 27 co-defendants includes a nearby road tender (Porto Romano–Durrës Road, Lot 3), no criminal indictment exists on the commercial port works contract itself. (2026-11-24)

The Porto Romano commercial port relocation project (Albanian: Projekti i portit të ri tregtar në Porto Romano) is the state-funded infrastructure program required to relocate commercial freight operations out of central Durrës so that the historic port site can be converted into the Durrës Yachts & Marina residential and yachting development.[1][2] Unlike the private-majority marina joint venture, Phase I of the Porto Romano commercial port—estimated at 39.3 billion ALL (~€393 million), and up to €399 million in broader budget estimates—remained entirely the responsibility of the Albanian state budget after international financial institutions did not provide financing or guarantees.[2][3]

Between 2024 and 2026, the relocation became the most severe financial, procurement, and environmental bottleneck of the wider Port of Durrës transformation. Following two stalled restricted-tender cycles, the European Commission's Albania 2026 Report (4 November 2026) confirmed that the tender had been cancelled after the sole remaining bidder failed to submit a final financial offer, leaving cargo relocation unstarted four years after Law No. 79/2022 was enacted.[4][5]

Procurement deadlock and tender cancellations (2024–2026)

Open Data Albania director Aranita Brahaj, cited by Osservatorio Balcani e Caucaso Transeuropa (OBCT), assessed the absence of international financial institution backing for Porto Romano as an indicator of low external confidence in how the dual Durrës–Porto Romano restructuring was designed.[2] The Durrës Port Authority (APD) procurement record shows repeated breakdowns:

  1. First tender cancelled (July 2024): A restricted procurement procedure with a 39.3 billion ALL (~€393 million) ceiling opened in July 2024 was cancelled due to the lack of suitable bids.[2]
  2. Re-tender, disqualifications, and KPP appeal (December 2024 – April 2025): APD reopened the tender on 24 December 2024.[2] On 4 April 2025, APD qualified two consortia—Archirodon (teamed with Deme Dredging NV and Società Italiana Dragaggi S.p.A.) and Van Oord (with Besix)—while disqualifying China Communications Construction Company, Webuild SpA, and Belgian dredging contractor Jan De Nul nv, which filed a formal appeal with the Public Procurement Commission (KPP) on 14 April 2025.[2] In January 2026, the investigative program Vetting raised transparency questions regarding the procedure and alleged offshore ties linked to one of the competing bidders.[6]
  3. Second cancellation confirmed by the European Commission (November 2026): The European Commission's Albania 2026 Report (4 November 2026) officially confirmed that the Porto Romano commercial port tender was cancelled because the sole remaining bidder did not submit its final financial bid within the deadline.[4] Both the 2024 and 2026 European Commission reports noted that no concrete steps had been taken to relocate freight operations from Durrës and warned that preventing corruption is critical to guarding the transport and logistics chain against criminal infiltration.[5][4]

EU competition scrutiny, environmental hazards, and social impact

European officials previously cautioned that strategic port projects must respect competition, transparency, equal treatment, and non-discrimination obligations under the Stabilisation and Association Agreement (SAA)—a warning voiced by EU Enlargement Commissioner Olivér Várhelyi.[2] While the European Commission's November 2026 report noted Albania's new PPP law (adopted December 2025, effective September 2026) abolishing unsolicited proposals, it specifically cautioned that new exemptions from public tendering—such as amendments to the law on tourist ports—require careful scrutiny.[4]

On environmental and social impacts, a Carnegie Endowment for International Peace report (8 December 2025) documented three structural risks at Porto Romano:

  • Industrial contamination & Fllaka Lagoon: Porto Romano is a historically polluted industrial zone containing petroleum deposits and chemical waste; marine dredging risks mobilizing toxic heavy-metal sediments adjacent to Fllaka Lagoon, a BirdLife International Key Biodiversity Area.[7]
  • Seismic vulnerability: Local urbanist Artan Kacani raised concerns over seismic sensitivity along the Porto Romano coastline.[2]
  • Fishing cooperatives & consultation: Local fishing cooperatives lost mooring spaces without clear compensation mechanisms, while public consultations operated more as "choreography" than genuine civic oversight.[7]

Parliamentary inquiry refusal and SPAK procedural distinction

On 17 December 2024, the Democratic Party's request for a parliamentary inquiry committee explicitly included the Porto Romano procurement alongside the Durrës Marina contract and the €13 million EMS–Scapha eastern terminal concession transfer; the Socialist majority rejected the request on 23 December 2024.[3][8]

In late December 2025, Albanian media reported SPAK verifications and document seizures linked to the ~€393 million Porto Romano port tender.[9] Separately, on 16 November 2026, SPAK sent former Deputy Prime Minister Belinda Balluku and 27 co-defendants (including former ARRSH officials) to trial under Criminal Proceeding No. 136/2025 over 10 road-infrastructure tenders, including "Construction of the Porto Romano–Durrës Road, Lot 3 (continuation)."[10] That road-tender indictment is legally distinct from the cancelled Porto Romano marine port works tender and from Law No. 79/2022.[10]

See also

References

  1. ↑BIRN "Probe Confirms Subsidence of Two Buildings at Billion-Euro Durrës Marina Project" . BIRN Albania / Reporter.al. 2026-05-13 .
  2. ↑ a b c d e f g h PressElira Kadriu. "Port of Durrës: plans proceed amid opacity and benefits for the few" . Osservatorio Balcani e Caucaso Transeuropa (OBCT) / Citizens.al. 2025-08-20 .
  3. ↑ a b Press "Illegality in the procedures / PD demands parliamentary investigation into the Durrës Marina & Yachts project and the port of Porto Romano" . BalkanWeb / News24. 2024-12-17 .
  4. ↑ a b c d EU / OSCE "Albania 2026 Report" . European Commission. 2026 .
  5. ↑ a b EU / OSCE "Albania 2024 Report" . European Commission. 2024-10-30 .
  6. ↑Press "Vetting: 393 million euros for the construction of Porto Romano — questions over Archirodon and offshore links" . Panorama / Vetting. 2026-01 .
  7. ↑ a b Press "Rules or Deals? The EU's Challenge in Regulating Corrosive Capital in the Western Balkans" . Carnegie Endowment for International Peace. 2025-12-08 .
  8. ↑BIRN "Mazhoranca refuzon hetimin parlamentar për Portin e Durrësit" . BIRN Albania / Reporter.al. 2024-12-23 .
  9. ↑Press "Tenderi 400 milionë euro i portit të ri të Durrësit nën hetim penal nga SPAK" . BoldNews. 2025-12-23 .
  10. ↑ a b Press "Sent Belinda Balluku and 27 other defendants to trial / SPAK official announcement reveals 10 tenders under investigation and seized assets of 1.8 million euros" . BalkanWeb / News24. 2026-11-16 .

Revision history

  • 2026-11-24 — Initial encyclopedic dossier on the Porto Romano commercial port relocation, procurement cancellations, EC 2024/2026 findings, Carnegie Endowment environmental analysis, and SPAK road-tender distinction.