This timeline tracks key legislative, corporate, constitutional, parliamentary, technical, and European Union milestones in the Port of Durrës Marina & Yachts project and the companion Porto Romano commercial port relocation from 2015 through November 2026.

  • 2015: Council of Ministers adopts VKM No. 949/2015 on the Albania–United Arab Emirates agreement for the promotion and protection of investments.[1]
  • September 2019: Symphony Invest Limited (Reg. No. 355663) is incorporated in the Cayman Islands, with its initial share transferred from WNL Limited to Mohamed Alabbar.[2]
  • 3 December 2020: The Parliament of Albania enacts Law No. 145/2020 ratifying the Albania–UAE Economic Cooperation Agreement; Article 6 exempts designated strategic projects from standard public procurement competition.[1]

2021–2022: Corporate vehicle, land transfer, and Law No. 79/2022

  • 9 May 2021: Ownership of Cayman-registered Symphony Invest Limited is split 50%/50% between two Abu Dhabi entities: Eastern RE Fund LP and Symphony Global Holdings Limited.[2]
  • 25 May 2021: Symphony Real Estate Development sh.p.k. (NIPT M11726006H, later renamed Eagle Hills Real Estate Development sh.p.k.) is incorporated in Albania with nominal capital of 10,000 ALL (~€100) and Symphony Invest Limited as sole owner.[2]
  • 2 December 2021: The Strategic Investment Committee (KIS) (Decision No. 14/6) grants the project seven-year "Strategic Investment/Investor — Special Procedure" status.[2]
  • 23 December 2021: Symphony Invest Limited transfers 100% of shares in the Albanian SPV—for 10,000 ALL—to North East Real Estate Holdings Limited (Abu Dhabi Global Market, UAE; authorized director Rashid Mohamed Ali Rashed Alabbar).[2]
  • 29 December 2021: Council of Ministers issues VKM No. 861, transferring 80.9 hectares of state land in Cadastral Zone 8514 from the Durrës Port Authority (APD) to the Strategic Investment Real Estate Support Fund.[3]
  • 27 January 2022: Parliament adopts Law No. 6/2022 strengthening the Beneficial Ownership Registry in line with MONEYVAL and EU directives.[4]
  • 22 June 2022: The Albanian subsidiary changes its legal name to Eagle Hills Real Estate Development sh.p.k.; a 6 October 2022 Beneficial Ownership Registry extract (effective 22 June 2022) lists Mohamed Ali Rashed Alabbar with 40.18% beneficial ownership.[2]
  • 8–10 November 2022: Draft framework agreement law is submitted to Parliament (8 November) and placed under accelerated procedure on 10 November with 62 votes (Article 83(2) of the Constitution).[5][6]
  • 12 November 2022: ACQJ publishes an early investigation comparing the framework bill and its off-plan "futures" pre-sales model to Belgrade Waterfront.[7]
  • 24 November 2022: Parliament enacts Law No. 79/2022 approving the €2.08 billion Framework Agreement covering 818,318 m² of public land without an international tender.[6]
  • December 2022: Off-plan apartment sales begin prior to construction ("sales in the pit") at €1,700–1,800/m².[7]

2023–2024: Joint venture, first court ruling, and inquiry refusal

  • 30 January – 23 February 2023: Joint venture Durrës Marina sh.a. is founded (30 Jan) and registered (23 Feb) with 67% held by Eagle Hills and 33% by state-owned ASDC.[2]
  • March 2023: ASDC formally assumes administration of 281 state-owned properties for the marina development.[8]
  • 16 June 2023: The Constitutional Court (Decision No. 36 / V-36/23) dismisses the first opposition petition (37 MPs) against Law No. 145/2020.[1]
  • September 2023: The National Territory Council (KKT) approves building permits for the first marina buildings on plots A02 and A04.[9]
  • July 2024: APD cancels the first 39.3 billion ALL (~€393M) restricted tender for the Porto Romano commercial port due to the lack of suitable bids.[10]
  • 30 October 2024: The European Commission's Albania 2024 Report notes that no concrete steps have been taken to relocate commercial cargo from Durrës.[11]
  • 17–23 December 2024: Thirty-five Democratic Party MPs (led by Gazment Bardhi) request a six-month parliamentary inquiry committee covering the marina, the €13M EMS–Scapha terminal transfer, and Porto Romano; on 23 December, the Socialist majority in the Conference of Speakers rejects the request.[6][12]
  • 24 December 2024: APD reopens the €393M Porto Romano commercial port tender.[10]

2025–2026: Second court ruling, subsidence, and EU confirmation

  • 21 February 2025: The Constitutional Court (Decision No. 8 / V-8/25) dismisses the Democratic Party's second petition against Law No. 79/2022 and four land-transfer VKMs.[13][3]
  • 4–14 April 2025: APD qualifies two consortia (Archirodon/Deme/SIDRA and Van Oord/Besix) for Porto Romano and disqualifies three others, including Jan De Nul nv, which appeals to KPP on 14 April.[10]
  • April 2025: National Democratic Institute (NDI) publishes its report documenting that under 5% of built area is dedicated to hotels/commerce and flagging beneficial-ownership monitoring gaps.[4]
  • 20 August 2025: OBCT / Citizens.al publishes an in-depth investigation detailing the 99-year stability clause, tax exemptions, offshore chain, and Porto Romano bottlenecks.[10]
  • 8 December 2025: Carnegie Endowment for International Peace publishes "Rules or Deals?", analyzing Durrës–Porto Romano governance, dredging pollution risks near Fllaka Lagoon, and displacement of local fishers.[14]
  • 23 December 2025: Media report SPAK verifications and document seizures linked to the €393M Porto Romano port tender.[15]
  • 13 May 2026: BIRN/Reporter.al reports that a joint inspection led by IKMT and the Construction Institute confirmed uneven subsidence of 28 cm in Building 02 and 18 cm in Building 04 at Durrës Marina and ordered structural reinforcements.[9]
  • 4 November 2026: The European Commission's Albania 2026 Report confirms the Porto Romano commercial port tender was cancelled after the sole remaining bidder failed to submit a final financial offer and reiterates that no concrete steps have been taken to relocate cargo.[16]
  • 16 November 2026: SPAK sends former Deputy Prime Minister Belinda Balluku and 27 co-defendants to trial in Proceeding No. 136/2025 covering 10 road tenders (including Porto Romano–Durrës Road, Lot 3)—a separate criminal file that does not indict Law No. 79/2022 or the Durrës Marina framework agreement.[17]

References

  1. ↑ a b c Court "Vendim Nr. 36, datë 16.06.2023 (V-36/23) mbi Ligjin nr. 145/2020 për Marrëveshjen e Bashkëpunimit Ekonomik Shqipëri–EBA" . Gjykata Kushtetuese e Republikës së Shqipërisë. 2023-06-16 (Vendimi Nr. 36 (V-36/23)) .
  2. ↑ a b c d e f g Official Record "Eagle Hills Real Estate Development sh.p.k. (formerly Symphony Real Estate Development) — NIPT M11726006H" . OpenCorporates Albania (QKB / Beneficial Ownership Registry extract). 2022-10-06 (NIPT M11726006H) .
  3. ↑ a b Press "Constitutional Court Rejects the DP's Appeal Against Durrës Tourist Port Project" . Euronews Albania. 2025-02-21 .
  4. ↑ a b Press "The Vulnerability of Albanian Politics to Foreign Interference" . National Democratic Institute (NDI). 2025-04 .
  5. ↑BIRN "Kuvendi fut me procedurë të përshpejtuar marrëveshjen sekrete për Portin e Durrësit" . BIRN Albania / Reporter.al. 2022-11-09 .
  6. ↑ a b c Press "Illegality in the procedures / PD demands parliamentary investigation into the Durrës Marina & Yachts project and the port of Porto Romano" . BalkanWeb / News24. 2024-12-17 .
  7. ↑ a b Press "Belgrade as a mirror for the Durrës Yachts & Marina project" . Albanian Center for Quality Journalism (ACQJ). 2022-11-12 .
  8. ↑Press "Durrës Yacht Marina, qeveria transferon 281 prona tek kompania" . Albanian Construction Portal (ACP). 2023-03 .
  9. ↑ a b BIRN "Probe Confirms Subsidence of Two Buildings at Billion-Euro Durrës Marina Project" . BIRN Albania / Reporter.al. 2026-05-13 .
  10. ↑ a b c d PressElira Kadriu. "Port of Durrës: plans proceed amid opacity and benefits for the few" . Osservatorio Balcani e Caucaso Transeuropa (OBCT) / Citizens.al. 2025-08-20 .
  11. ↑EU / OSCE "Albania 2024 Report" . European Commission. 2024-10-30 .
  12. ↑BIRN "Mazhoranca refuzon hetimin parlamentar për Portin e Durrësit" . BIRN Albania / Reporter.al. 2024-12-23 .
  13. ↑Court "Vendim Nr. 8, datë 21.02.2025 (V-8/25) mbi Ligjin nr. 79/2022 dhe VKM-të për projektin Marina & Jahtet e Durrësit" . Gjykata Kushtetuese e Republikës së Shqipërisë. 2025-02-21 (Vendimi Nr. 8 (V-8/25)) .
  14. ↑Press "Rules or Deals? The EU's Challenge in Regulating Corrosive Capital in the Western Balkans" . Carnegie Endowment for International Peace. 2025-12-08 .
  15. ↑Press "Tenderi 400 milionë euro i portit të ri të Durrësit nën hetim penal nga SPAK" . BoldNews. 2025-12-23 .
  16. ↑EU / OSCE "Albania 2026 Report" . European Commission. 2026 .
  17. ↑Press "Sent Belinda Balluku and 27 other defendants to trial / SPAK official announcement reveals 10 tenders under investigation and seized assets of 1.8 million euros" . BalkanWeb / News24. 2026-11-16 .

Revision history

  • 2026-11-24 — Initial chronological spine covering legal, corporate, parliamentary, constitutional, technical, and EU milestones for the Port of Durrës and Porto Romano projects (2015–2026).