| Tigri 1 and Tigri 3 floating power plants (2021–2026) | |
|---|---|
| Also known as | Tigri 1 & Tigri 3; Vlora floating thermal power plants (TEC-et lundruese); Albania Power Project |
| Date | October 2021 – ongoing (VKM 620/2021; KESH contract Apr 2022; operational start 13 Sept 2024; ERE suspension Sept 2026 & licensing 6 Nov 2026) |
| Location | Triport (near Vlora Thermal Power Plant), Vlorë, Albania |
| Type | Emergency energy procurement, fixed availability payments vs. low dispatch, commissioning delay, lifecycle-cost transparency gap, and environmental licensing suspension/resolution |
| Estimated value / cost | $94,500/day fixed obligation ($63,000 lease + $31,500 O&M; ~$68.985M 730-day ceiling); $65,141,511 paid in lease & O&M + ALL 1,904,254,854 for HFO, transport & insurance through Aug 2026 |
| Key participants |
|
| Institutions involved |
|
| Investigating bodies |
|
| Legal status / outcome | Audit / administrative findings No project-specific criminal charge, indictment, or conviction located through 24 Nov 2026. ERE suspended licensing on 3 Sept 2026 pending environmental-permit clarification and subsequently licensed KESH via Decision No. 337 on 6 Nov 2026. Core controversies remain value-for-money (~8.3% calendar hours and ~5.9% capacity factor through Aug 2026) and transparency gaps over KESH's €163/MWh cost formula and environmental monitoring records. |
The Tigri 1 and Tigri 3 floating power plants (Albanian: TEC-et lundruese "Tigri 1" dhe "Tigri 3") are two heavy-fuel-oil (HFO) power barges—Tigri 1 (50 MW) and Tigri 3 (60 MW), totaling 110 MW of regulatory installed capacity—stationed at Triport near the existing Vlora Thermal Power Plant and leased by Albania's state-owned electricity producer Albanian Power Corporation (KESH) from a joint venture of U.S.-listed Excelerate Energy (90%) and Italian engineering firm Renco S.p.A. (10%).[1][2][3]
Procured under Council of Ministers Decision (VKM) No. 620 of 22 October 2021 (amended by VKM No. 757 of 21 December 2021) during the 2021–2022 European energy-price crisis, the two-year temporary lease carries fixed daily obligations of $63,000/day in lease charges and $31,500/day in operation-and-maintenance (O&M) fees—$94,500/day combined, excluding fuel and VAT—implying a theoretical 730-day fixed ceiling of ~$68.985 million.[4][2]
Public scrutiny has centered on four documented issues: (1) thin competition under an emergency expression-of-interest call where only one of two applicants qualified; (2) a two-year commissioning delay, with commercial operation beginning on 13 September 2024 rather than in 2023 as anticipated in KLSH's audit; (3) the wide gap between fixed availability payments and actual generation—through 12 August 2026, KESH had paid $65,141,511 in lease and O&M fees plus ALL 1,904,254,854 for fuel, transport, and insurance while generating 109,125.55 MWh over roughly 1,392 operating hours (~8.3% of elapsed calendar hours); and (4) environmental permitting and cost transparency gaps, highlighted when the Energy Regulatory Authority (ERE) suspended licensing on 3 September 2026 before granting production licenses via Decision No. 337 on 6 November 2026.[2][4][5][6] Through 24 November 2026, no project-specific SPAK indictment, charge, or publicly verifiable criminal proceeding was located.[4]
Emergency legal basis, procurement, and contract terms (2021–2022)
Facing acute European wholesale electricity prices and Albania's heavy dependence on hydropower, the Council of Ministers adopted VKM No. 620 (22 October 2021), amended by VKM No. 757 (21 December 2021), authorizing KESH to lease temporary thermal generating assets for two years.[4] KESH published an international call for expressions of interest on 5 January 2022 and published its evaluation announcement on 13 April 2022.[2]
Only two expressions of interest were received: Excelerate Energy with Renco S.p.A., and Distributed Power Solution.[2] KESH determined that Distributed Power Solution did not meet the call's conditions, leaving Excelerate/Renco as the sole qualifying and winning offer.[2] While competitive in form, the emergency framework yielded thin competition and limited price discovery compared to a standard multi-bid tender.[2] Notably, KESH identifies the resulting contract as No. 1660/1, dated 4 April 2022—nine days prior to the 13 April public evaluation notice—an unexplained chronology discrepancy in public records that merits clarification from the full negotiation file rather than serving as proof of preselection.[7]
| Contract / Operating Parameter | Documented Public Figure |
|---|---|
| Installed capacity | 110 MW regulatory total (50 MW Tigri 1 + 60 MW Tigri 3); 19 Wärtsilä-type generating sets (typically 17 active + 2 reserve). (KLSH also cites 114 MW in one section based on 19 × 6 MW nominal engines; ERE licenses confirm 110 MW.)[1][6][4] |
| Minimum contractual availability | 85% (availability obligation, not mandatory dispatch).[2] |
| Fixed daily lease charge | $63,000/day (excl. fuel and VAT).[4] |
| Fixed daily O&M charge | $31,500/day (excl. fuel and VAT).[4] |
| Combined fixed daily obligation | $94,500/day (~$68.985M arithmetic 730-day ceiling).[4] |
| Original KESH/KLSH cost estimate | ~€202/MWh (excluding excise in the stated KLSH scenario).[4] |
| Fuel specification | Heavy Fuel Oil (HFO/VLSFO) primary (~220 kg/MWh contractual specific consumption; 0.5% sulphur in KLSH model); lighter fuel secondary/backup.[2][4] |
| Contract term & end-of-term transfer | Two years from delivery/commissioning; KESH's tender notice stated the barges and ancillary infrastructure would remain KESH property after the rental period.[2][7] |
Corporate filings confirm the consortium's ownership split: Excelerate Energy's U.S. SEC EDGAR filings disclose that it established an "Albania Power Project" entity in April 2022 and holds 90% of it, while Renco S.p.A.'s financial statements report a 10% interest in Excelerate-Renco FPB in Albania.[3] Renco's 2023 Sustainability Report (published September 2024) describes the venture as an Italian-American project in which Renco handled installation and final testing after sourcing and transporting the barges.[8]
Commissioning delay, cumulative payments, and low utilization (2022–2026)
Although KLSH's 2021–2022 performance audit (RA08521) anticipated entry into operation in 2023, KESH informed transparency applicants in July 2024 that commissioning and certification remained incomplete, and now records operational start as 13 September 2024—roughly two years after contracting.[4][7] Crucially, KESH states that contractual payments attached to delivery/takeover and commissioning rather than the April 2022 signature date—meaning public claims that Albania paid $94,500/day continuously from April 2022 while producing zero power are not supported by KESH's payment disclosures.[7]
KESH's successive Transparency Register disclosures document verified cumulative payments and generation:
| KESH Disclosure Date | Lease (Excelerate–Renco) | Renco O&M | Cumulative Generation |
|---|---|---|---|
| June 2025 | $23,979,600.33 | $9,109,800 | 62,423.81 MWh[7] |
| September 2025 | $28,662,894.47 | $11,415,600 | 71,684.59 MWh[7] |
| Nov/Dec 2025 reporting | $32,998,715.85 | $14,893,200 | 92,012.69 MWh[7] |
| 27 August 2026 | $44,131,011 | $21,010,500 | 109,125.55 MWh[5] |
In addition to $65,141,511 in combined lease and O&M disbursements through August 2026, KESH contracted Europetrol Durrës Albania (Contract 415/3, 23 February 2024, value ALL 301,386,454) and Emad Energy (Contract 4809, 30 September 2024, value €12,155,381) for fuel supply.[7] For fuel actually attributed to electricity generation through 12 August 2026, KESH reported consuming 25,358.33 tonnes of HFO costing ALL 1,546,810,307, plus ALL 9,870,696 for transport and ALL 347,573,851 for insurance (reporting zero under the specific ongoing mooring-services line), bringing directly identified non-USD operating expenditure to ALL 1,904,254,854.[5]
Over the roughly 23-month period from 13 September 2024 to 12 August 2026, KESH reported approximately 1,392 actual production hours, equating to an approximate calendar utilization of ~8.3% of elapsed hours and an approximate calendar capacity factor of ~5.9% of the 110 MW maximum.[5] Because the contract stipulated 85% availability rather than continuous baseload generation, and KESH states the units were dispatched deliberately as reserve capacity when system needs required, low utilization does not establish contractual breach.[5] Similarly, while KESH reported an overall calculated generation cost of ~€163/MWh in August 2026 (below KLSH's earlier ~€202/MWh estimate), the absence of a published accounting reconciliation explaining how fixed lease payments, O&M, fuel, insurance, taxes, and end-of-term asset ownership are allocated across generated MWh remains a significant transparency gap.[5]
Environmental permitting and ERE 2026 licensing sequence
Because the barges burn heavy fuel oil near the Vlora coast, environmental compliance is a central public-interest issue. KESH's procurement terms referenced HFO/VLSFO sulphur limits and IFC/World Bank 2017 emissions guidelines.[2] In 2026, regulatory friction became public at the Energy Regulatory Authority (ERE):
- On 6 July 2026, ERE opened a new production-licensing procedure for KESH covering Tigri 1 and Tigri 3.[6]
- On 3 September 2026, ERE suspended the licensing procedure while environmental-permit issues were being clarified.[6][9]
- On 6 November 2026, ERE adopted Decision No. 337, formally licensing KESH for electricity production from Tigri 1 and Tigri 3.[6][10]
This regulatory sequence confirms a genuine environmental-administrative uncertainty in mid-2026 that was subsequently resolved by ERE rather than an ongoing finding of illegal operation.[6] Nevertheless, the underlying National Environment Agency (AKM) environmental permit files and complete public series of marine-water-temperature monitoring, stack-emissions measurements, HFO spill-risk assessments, and compliance inspections remain unavailable in public databases.[6]
Audit and prosecutorial status (as of November 2026)
- KLSH (
RA08521): KLSH's performance audit of KESH recorded the $94,500/day commitment and ~€202/MWh planning estimate, but did not make a project-specific finding that the Excelerate/Renco contract was corruptly or unlawfully awarded (KLSH's broader 2021–2022 audit identified unrelated KESH compliance deficiencies that cannot be attributed to Tigri).[4] - SPAK: Although Democratic Party MP Gazment Bardhi filed a criminal complaint with SPAK against former Minister Belinda Balluku alleging €70–80 million in public-fund abuse, no project-specific SPAK indictment, criminal charge, judgment, or publicly verifiable criminal proceeding concerning Excelerate Energy, Renco, or KESH officials over Tigri 1/3 was located through 24 November 2026 (an absence of public evidence rather than proof that no confidential inquiry exists).[11]
Evidence gaps
Key missing primary records include the full signed Excelerate/Renco lease-and-O&M agreement and amendments; negotiation minutes and price-comparison analyses; the legal explanation for the 4 April 2022 contract date preceding the 13 April evaluation notice; delivery and commissioning certificates; a reconciled lifecycle-cost model explaining the €163/MWh figure; complete AKM environmental permits and monitoring datasets; and documentation establishing the exact date and terms of asset ownership transfer to KESH.[5][7]
See also
Notes
- The contract's 85% threshold is an availability requirement rather than a mandatory generation requirement; low actual dispatch (~8.3% of elapsed calendar hours) does not by itself establish contractual breach.
- KESH's August 2026 payments ($65,141,511 in USD lease/O&M plus ALL 1,904,254,854 in Albanian lek for HFO, transport, and insurance) are reported in their original currencies to avoid exchange-rate distortion across multi-year payment dates.
- No verified corporate, beneficial-ownership, or contractual link exists between Excelerate Energy / Renco S.p.A. and the Vlora International Airport consortium (Mabco/YDA/2A Group).
References
- ↑ a b Official Record "TEC Lundrues — Tigri 1 dhe Tigri 3" . Albanian Power Corporation (KESH) .
- ↑ a b c d e f g h i j k Official Record "Notification for the Evaluation of the Expression of Interest (Floating Thermal Power Plants)" . Albanian Power Corporation (KESH). 2022-04-13 .
- ↑ a b Official Record "Excelerate Energy, Inc. — SEC EDGAR Filing (90% ownership of Albania Power Project)" . U.S. Securities and Exchange Commission (SEC). 2026 .
- ↑ a b c d e f g h i j k l KLSH Audit "Raport auditimi i performancës në Korporatën Elektroenergjitike Shqiptare (KESH) — RA08521" . Kontrolli i Lartë i Shtetit (KLSH). 2025-02 (RA08521) .
- ↑ a b c d e f g Official Record "Regjistri i Transparencës 2026 — Përgjigje për TEC-et lundruese Tigri 1 dhe Tigri 3 (27 gusht 2026)" . Albanian Power Corporation (KESH). 2026-08-27 .
- ↑ a b c d e f g Official Record "Vendimet e Bordit 2026 (Pezullimi 3 shtator 2026 dhe Vendimi nr. 337, 6 nëntor 2026 — Tigri 1 dhe Tigri 3)" . Energy Regulatory Authority (ERE). 2026-11-06 .
- ↑ a b c d e f g h i Official Record "Regjistri i Transparencës Arkiva (2024–2025) — TEC-et lundruese" . Albanian Power Corporation (KESH). 2025 .
- ↑Official Record "Renco S.p.A. — Sustainability Report 2023 (Bilancio di sostenibilità 2023)" . Renco S.p.A.. 2024-09 .
- ↑Press "ERE nuk licencon TEC-et lundruese në Vlorë: Pezullim për 'Tigri 1' e 'Tigri 3' për lejet mjedisore" . Shqiptarja.com. 2025 .
- ↑Press "ERE licenson 'Tigri 1' dhe 'Tigri 3', dy centralet lundrues në Vlorë" . Patriotik Media. 2026-11-22 .
- ↑Press "'11.3 kg prova', Bardhi kallëzon Belinda Ballukun në SPAK për dy TEC-et lundruese në Vlorë" . Shqiptarja.com. 2025 .
Revision history
- 2026-11-24 — Initial bilingual dossier authored from the Vlora infrastructure intake dossier, KESH EOI evaluation (13 Apr 2022), KESH Transparency Registers (2024–2026, incl. 27 Aug 2026 response), KLSH audit RA08521, ERE 2026 Board Decisions (incl. Decision No. 337), U.S. SEC Excelerate Energy filing, and Renco S.p.A. reporting.