| Milot–Balldre highway concession and re-tenders (2018–2026) | |
|---|---|
| Also known as | Milot–Balldren PPP (Law No. 52/2019); Blue Corridor Milot–Balldre tolled concession |
| Date | 2018 – ongoing (Law 52/2019 vetoed 8 Aug 2019 & overridden; original ANK contract lapsed late 2020; Dec 2024 re-tender canceled 14 Jul 2025; reopened Aug 2025) |
| Location | Milot–Balldre segment (17.2 km), Lezhë County, Albania |
| Type | Unsolicited-proposal road PPP approved by special parliamentary law, presidential veto dispute, financing failure, and subsequent Blue Corridor re-tenders |
| Estimated value / cost | Original 2018–2019 ANK PPP: ~€161.5M–€256M (excl./incl. financing & VAT over 13 yrs); 2024–2025 Blue Corridor 35-year tolled re-tender: ~€364.7M |
| Key participants |
|
| Institutions involved | |
| Legal status / outcome | Political / transparency controversy No criminal charges have been filed. Parliament overrode President Meta's August 2019 veto of Law No. 52/2019, but the original ANK concession lapsed in late 2020 after ANK failed to secure financing. A redesigned 35-year tolled tender (€364.7M) opened in December 2024 was canceled on 14 July 2025 for lack of compliant bids and reopened in August 2025. |
The Milot–Balldre highway concession refers to a series of contested Public-Private Partnership (PPP) procedures launched between 2018 and 2025 to design, build, and maintain the 17.2-kilometer Milot–Balldre road corridor in northern Albania.[1][2] Initially awarded via an unsolicited proposal to ANK sh.p.k. and Bardh Konstruksion sh.p.k. and ratified by Parliament through Law No. 52/2019, the contract drew a formal veto from President Ilir Meta on 8 August 2019 before collapsing in late 2020 after ANK failed to secure project financing.[3][1][2] A redesigned 35-year tolled concession (~€364.7 million) launched in December 2024 was subsequently canceled on 14 July 2025 due to the absence of compliant bids.[2][4]
2018–2019 ANK unsolicited PPP and Law No. 52/2019
In 2018, the Ministry of Infrastructure and Energy (MIE) advanced an unsolicited PPP proposal for the Milot–Balldre segment submitted by ANK sh.p.k. (jointly with Bardh Konstruksion sh.p.k.), granting an unsolicited-proposal bonus under Albanian concession rules.[1] In July 2019, the Socialist parliamentary majority enacted Law No. 52/2019, ratifying the 13-year concession contract directly by special statute.[3][1]
On 8 August 2019, President Ilir Meta formally returned Law No. 52/2019 to the Parliament of Albania for reconsideration.[3][1] In his accompanying decree, the Presidency argued that:
- The contract had been drafted, signed, and approved in violation of the rule of law, free competition, and equality before the law;[1]
- The project lacked clear economic evaluation and mandatory approval from the Ministry of Finance, exposing the state budget to substantial fiscal risk;[3][1]
- The government had disregarded repeated recommendations from international financial institutions to abolish unsolicited PPP proposals;[1]
- Ratifying the contract by special parliamentary law was used to shield procedural irregularities from standard administrative scrutiny.[3]
The parliamentary majority subsequently overrode President Meta's veto, allowing Law No. 52/2019 to enter into force.[1]
Late-2020 contract failure and 2024–2025 Blue Corridor re-tenders
Despite parliamentary ratification, construction never began under the ANK contract. By late 2020, MIE confirmed that the original 13-year concession (valued at ~€161.5 million in base construction terms and higher with financing and VAT) had lapsed because ANK failed to meet contractual prerequisites and secure bank financing.[2]
In December 2024, MIE redesigned the segment as a 35-year tolled concession integrated into the Adriatic–Ionian Blue Corridor with an estimated investment value of approximately €364.7 million.[2][4] On 14 July 2025, the contracting authority formally canceled the re-tender after concluding that none of the participating consortia—which included major domestic contractors such as Gener 2, Salillari, ANK, and 4 A-M—had submitted a compliant offer, prompting a renewed procurement cycle later in 2025.[4]
Legal status
As of 25 November 2026, no criminal charges or prosecutions have been brought against Edi Rama, Belinda Balluku, or private contractors regarding the Milot–Balldre concession procedures. The dossier remains a documented case of contested special-law PPP governance, presidential constitutional objection, and repeated procurement failure.[1][4]
See also
References
- ↑ a b c d e f g h i j BIRN "Meta kthen pas ligjin për koncesionin e rrugës Milot-Balldren" . BIRN / Reporter.al. 2019-08-08 .
- ↑ a b c d e Press "Rruga Milot-Balldre do të jetë me pagesë për qytetarët! Në dhjetor hapet gara për koncesionin për ndërtimin e këtij segmenti - Shqiptarja.com" . shqiptarja.com .
- ↑ a b c d e Official Record "Presidenti Meta ka dekretuar kthimin për rishqyrtim në Kuvend të ligjit nr. 52/2019 (Koncesioni/PPP Milot–Balldren)" . Presidency of the Republic of Albania (arkiva.president.al). 2019-08-08 .
- ↑ a b c d PressEkofin. "Anulohet koncesioni i rrugës Milot-Balldre, “asnjë ofertë e përshtatshme” - Ekofin" . ekofin.al. 2025-07-14 .
Revision history
- 2026-11-25 — Initial bilingual dossier documenting the 2018–2020 ANK unsolicited PPP, Law No. 52/2019 presidential veto, late-2020 financing collapse, and 2024–2025 Blue Corridor tolled re-tenders.