This chronology traces the Osum Canyons hydropower scandal, the corporate history of concessionaire HP Bigas dhe Veleshnje Energy sh.p.k., and the administrative court proceedings from September 2013 through 2026.

2013–2016 — Concession award, corporate formation, and expansion

  • 6 September 2013: At the end of its governing mandate, Sali Berisha's administration approves a concession contract for three small hydropower plants (Bigas 1, Bigas 2, and Veleshnje) in the Osum River basin in Skrapar.[1]
  • 27 September 2013: HP Bigas dhe Veleshnje Energy sh.p.k. (QKB NIPT L39604401K) is registered in Berat as a 100%-owned subsidiary of 2 AF sh.p.k.[1][2]
  • 26 March 2015: The National Environment Agency (AKM) approves Preliminary EIA Decision No. 13 (ID No. 137) for Bigas 1 and Bigas 2 under Clause 8.2, setting a two-year deadline for construction to begin.[3][4]
  • 16 May 2016: The Ministry of Energy and Industry under Damian Gjiknuri amends the concession contract, merging Bigas 1 and Bigas 2 and increasing planned installed capacity from 0.5 MW to 1.2 MW.[5]

2017 — Official warning, EIA expiration, and unpublished KKT permit

  • 9 March 2017: Speaker of Parliament Ilir Meta sends an official warning letter ("Shqetësime ndaj projektit mbi lumin Osum") to Environment Minister Lefter Koka, copied to Prime Minister Edi Rama and Energy Minister Damian Gjiknuri, warning of irreversible damage to the Bigas waterfalls and flagging missing parcel 36 and water-use permits.[1]
  • 26 March 2017: The two-year statutory window in Preliminary EIA Decision No. 13/ID 137 expires without construction starting, rendering the environmental clearance legally invalid under Clause 8.2.[3]
  • 12 December 2017: The National Territory Council (KKT), chaired by Prime Minister Rama, approves the development permit for the Bigas and Veleshnje HPPs nearly nine months after both the EIA's expiry and Meta's warning letter; the decision is not published.[1]

2018 — Internal memo, media exposure, rollback, and KLSH audit

  • 8 January 2018: Tourism and Environment Minister Blendi Klosi sends an official memorandum to Infrastructure and Energy Minister Damian Gjiknuri requesting cancellation of the concession.[3]
  • 7–9 February 2018: Gazeta TemA (7 Feb) and Top Channel (8 Feb) expose alleged coordinate manipulation and the expired 2015 EIA; on 9 February, Rama announces project cancellation on Facebook while BIRN publishes Meta's March 2017 warning letter, and MTM/ISHMPU issue Notice No. 638 suspending works.[6][3][1][4]
  • 15 February 2018: MTM issues Decision No. 1, declaring Preliminary EIA Decision No. 13 (ID No. 137) absolutely invalid due to false data on water quantity and coordinates.[7][4]
  • 19 February 2018: MIE formally notifies the concessionaire of unilateral contract termination under Article 12.[7][8]
  • 23 February 2018: Prime Minister Rama pledges "no HPP where tourism is harmed".[9]
  • 18 April 2018: Tirana First Instance Administrative Court Judge Afërdita Maho admits the concessionaire's lawsuit for merits review while rejecting a motion to suspend cancellation acts.[5]
  • 8 May & 17 September 2018: On 8 May, AKZM reverses its earlier clearance and confirms Bigas I sits inside the Osum Canyons Natural Monument under Law No. 81/2017; on 17 September, KLSH Audit No. 1086/1 documents AKZM's contradictory spatial certifications.[10]
  • 30 July 2018: Judge Maho dismisses HP Bigas dhe Veleshnje Energy's lawsuit in full on public-interest grounds following the secondary intervention of EcoAlbania and the Albanian Rafting Federation (represented by the Durrës Law Clinic / OSFA); BIRN notes zero judicial criminal referrals.[4][11]
  • 26 December 2018: The concessionaire re-applies for a permit using identical documentation and files a second suit; AKZM rejects the permit and expands the protected zone.[12]

2019–2026 — Appellate victory and long-tail litigation

  • 7 March 2019: The Administrative Court of Appeal upholds cancellation of all three HPPs in the Osum Canyons.[12]
  • 19 March 2019: Monitor.al reports ongoing appellate litigation by the company against MTM, AKM, and AKZM seeking to compel EIA approval.[13]
  • 2025–2026: Administrative proceedings continue on the Administrative Court of Appeal docket (November 2025) and appear on the Supreme Court of Albania administrative deliberation chamber docket in 2026 under Case No. 31001-00320-00-2026.[14][15]

References

  1. ↑ a b c d e BIRN "Rama u paralajmërua nga Meta, por i firmosi HEC-et në Osum në dijeni të shkeljeve" . BIRN Albania / Reporter.al. 2018-02-09 .
  2. ↑Official Record "HP Bigas dhe Veleshnje ENERGY (NIPT L39604401K)" . OpenCorporates Albania / QKB. 2024-04-11 (QKB NIPT L39604401K) .
  3. ↑ a b c d Press "Ekskluzive / Leja mjedisore e HEC-eve mbi kanionet e Osumit, e skaduar" . Top Channel. 2018-02-08 (AKM Decision No. 13 / ID No. 137 (26.03.2015), Clause 8.2; MTM Memo (08.01.2018)) .
  4. ↑ a b c d Press "Gjykata rrëzon HEC-et mbi Kanionet e Osumit" . Gazeta TemA. 2018-07-31 (MTM Decision No. 1 (15.02.2018); AKM Decision No. 13/ID 137 (26.03.2015); Notice No. 638 (09.02.2018)) .
  5. ↑ a b BIRN "HEC-et në kanionet e Osumit; koncesionari sfidon kryeministrin në gjykatë" . BIRN Albania / Reporter.al. 2018-04-25 .
  6. ↑Press "FAKSIMILE: Thellohet skandali, Ministria e Mjedisit manipuloi koordinatat për ndërtimin e HEC-eve në Osum" . Gazeta TemA. 2018-02-07 .
  7. ↑ a b BIRN "Fillimi i fundit për kontratën e HEC-eve në lumin Osum" . BIRN Albania / Reporter.al. 2018-02-19 .
  8. ↑Official Record "HEC-et në Osum, MIE nis procedurat për zgjidhjen e kontratës" . Ministry of Infrastructure and Energy (MIE). 2018-02-19 (Article 12 Concession Contract Termination Notice (19.02.2018)) .
  9. ↑Press "Rama zotohet: Asnjë HEC aty ku cenohet turizmi" . Top Channel. 2018-02-23 .
  10. ↑Press "HEC-et, "peshqeshi" për zonat e mbrojtura, banorët humbën ujin dhe turizmin" . Albanian Center for Quality Journalism (ACQJ) & Amfora.al. 2018 (KLSH Audit No. 1086/1 (17.09.2018)) .
  11. ↑BIRN "Gjykata Administrative vulos anulimin e HEC-eve në kanionet e Osumit" . BIRN Albania / Reporter.al. 2018-07-31 .
  12. ↑ a b Press "Shoqëria civile nis betejën në gjykata për projektet mjedisore" . Porta Vendore. 2019-04-26 .
  13. ↑Press "Koncesionarët "mësyjnë" gjykatën, markimi i karburanteve, HEC-et mbi Osum kundër institucioneve" . Monitor.al. 2019-03-19 .
  14. ↑Court "Shpallur më 21.10.2025 — Gjykata Administrative e Apelit" . Gjykata Administrative e Apelit (Administrative Court of Appeal). 2025-10-21 .
  15. ↑Court "Për shqyrtim në dhomë këshillimi - Administrative (Çështja Nr. 31001-00320-00-2026)" . Gjykata e Lartë e Republikës së Shqipërisë (Supreme Court of Albania). 2026 (Case No. 31001-00320-00-2026) .

Revision history

  • 2026-11-23 — Initial chronological dossier tracing the Osum Canyons HPP concession from September 2013 award through the 2018 scandal and 2026 Supreme Court docket.