Alban (Albano) Feta has not been criminally charged or convicted in any proceeding documented in this archive. He served as the legal administrator of the concessionaire company whose Osum Canyons HPP permits were revoked in 2018 and upheld by administrative courts in 2018–2019. (2026-11-23)

Alban (Albano) Feta is an Albanian business administrator who managed HP Bigas dhe Veleshnje Energy sh.p.k., the special-purpose concessionaire behind the contested Bigas 1, Bigas 2, and Veleshnje small hydropower plants in the Osum Canyons.[1][2]

Role in the Osum Canyons concession and litigation (2013–2026)

Main articles: HP Bigas dhe Veleshnje Energy and Osum Canyons hydropower administrative litigation

Registered in Berat on 27 September 2013 (QKB NIPT L39604401K), HP Bigas dhe Veleshnje Energy sh.p.k. is wholly owned by parent firm 2 AF sh.p.k.—whose sole shareholder is reported by BIRN as Erfan Feta—and administered by Alban Feta.[1][2] Under his management, the company obtained Preliminary EIA Decision No. 13/ID 137 on 26 March 2015, secured a capacity expansion to 1.2 MW from Damian Gjiknuri's Ministry of Energy and Industry on 16 May 2016, and received an unpublished development permit from the National Territory Council (KKT) on 12 December 2017.[3][1]

Following February 2018 media disclosures of expired environmental clearance and manipulated spatial coordinates—later corroborated by KLSH Audit No. 1086/1 confirming that the Bigas I structure fell inside the Osum Canyons Natural Monument—Blendi Klosi's Ministry of Tourism and Environment invalidated the 2015 EIA on 15 February 2018 and Gjiknuri's ministry initiated unilateral contract termination on 19 February 2018.[4][5][6] Represented by attorney Anxhelo Feta (Haxhia dhe Hajdari), the company contested the revocation in administrative court, losing at First Instance (30 July 2018) and the Administrative Court of Appeal (7 March 2019), while continuing lingering administrative appeals into the Supreme Court of Albania docket in 2026 (Case No. 31001-00320-00-2026).[3][7][8] No criminal charges or convictions against Feta are documented in reviewed public records.[9]

See also

References

  1. ↑ a b c BIRN "Rama u paralajmërua nga Meta, por i firmosi HEC-et në Osum në dijeni të shkeljeve" . BIRN Albania / Reporter.al. 2018-02-09 .
  2. ↑ a b Official Record "HP Bigas dhe Veleshnje ENERGY (NIPT L39604401K)" . OpenCorporates Albania / QKB. 2024-04-11 (QKB NIPT L39604401K) .
  3. ↑ a b BIRN "HEC-et në kanionet e Osumit; koncesionari sfidon kryeministrin në gjykatë" . BIRN Albania / Reporter.al. 2018-04-25 .
  4. ↑BIRN "Fillimi i fundit për kontratën e HEC-eve në lumin Osum" . BIRN Albania / Reporter.al. 2018-02-19 .
  5. ↑Press "HEC-et, "peshqeshi" për zonat e mbrojtura, banorët humbën ujin dhe turizmin" . Albanian Center for Quality Journalism (ACQJ) & Amfora.al. 2018 (KLSH Audit No. 1086/1 (17.09.2018)) .
  6. ↑Official Record "HEC-et në Osum, MIE nis procedurat për zgjidhjen e kontratës" . Ministry of Infrastructure and Energy (MIE). 2018-02-19 (Article 12 Concession Contract Termination Notice (19.02.2018)) .
  7. ↑Press "Shoqëria civile nis betejën në gjykata për projektet mjedisore" . Porta Vendore. 2019-04-26 .
  8. ↑Court "Për shqyrtim në dhomë këshillimi - Administrative (Çështja Nr. 31001-00320-00-2026)" . Gjykata e Lartë e Republikës së Shqipërisë (Supreme Court of Albania). 2026 (Case No. 31001-00320-00-2026) .
  9. ↑BIRN "Gjykata Administrative vulos anulimin e HEC-eve në kanionet e Osumit" . BIRN Albania / Reporter.al. 2018-07-31 .

Revision history